Summary
Data centers with an installed power demand of at least 500 kW are required to submit an annual report on energy efficiency through the European platform. The first deadline is set for September 15, 2024.
Key points
Check the
In detail
Conditions
Be a data center with an installed power demand of at least 500 kW.
Procedure
- Access the reporting platform via this
link . - Create an EU Login account if you don’t have one. You can consult the
FAQ for more details. - Follow the steps described to submit your data.
- During your first login, authorization will be requested from SPW to validate your access.
Délais
The first report must be submitted by September 15, 2024, and annually before May 15 thereafter.